Winnipeg faces potential sewage-treatment crunch, even with improvements underway
Winnipeg could run out of sewage-treatment capacity as much as one year before the completion of improvements that should expand that capacity, a report to city council says. Winnipeg's three sewage-treatments plants are capable of processing all the existing
Illustrative imageWinnipeg could run out of sewage-treatment capacity as much as one year before the completion of improvements that should expand that capacity, a report to city council says.
Winnipeg's three sewage-treatments plants are capable of processing all the existing and expected residential and industrial wastewater in the city until late 2029, according to a worst-case scenario presented by water and waste engineers in a report to city council published Tuesday.
A processing facility planned to convert partly treated sludge from all three of those plants into biosolids, slated for construction at the North End Water Pollution Control Centre, is not expected to be finished until the final three months of 2030, the report also states.
This creates the potential for a one-year sewage-treatment crunch, albeit only if the city grows more quickly than expected or new industrial businesses that consume a tremendous amount of water begin operating in the city, the report states.
"Those brand new digesters, it's going to be pretty close," said Tim Shanks, Winnipeg's water and waste director.
"We're on schedule, on budget and feel pretty good about that project right now. But we're not going to hang our hat on that alone.
"We are working on some other contingencies in case there's a gap there between the finishing of that project."
Right now, the city has enough capacity to handle sewage for another 25,000 to 35,000 people, which is the city's expected growth by the end of 2029, water and waste engineering manager Cynthia Wiebe wrote in the report to council.
At the same time, the completion of the first phase of improvements to the North End plant — a new headworks that screens out rags, dirt and sand — might improve capacity long enough for the new biosolids facility to come online the next year, she said.
The third phase of the improvements at the North End plant, a new facility that will remove phosphorus and nitrogen from the city's wastewater, is expected to be finished in 2032.
This should provide two more decades of treatment capacity, the report said.
All three levels of government have committed to funding this final component of the $3.2-billion project.
It was originally envisioned in 2003, the year after a major sewage spill at the North End sewage treatment plant sparked a provincial order to improve sewage treatment at all three city plants.